CL-WP-004 / WORKING PAPER / v1.0

Peak Water, Not Average Water.

A reproducible public-evidence capacity screen for data-center growth in Loudoun County, Northern Virginia.

Abstract. This release tests how published utility and regional water evidence can be translated into a transparent compute-capacity screen without treating annual averages, nominal future system capacity, reclaimed supply and hydrologic consumption as interchangeable quantities. The contribution is a peak-water screening method and evidence workflow—not a utility will-serve determination or a final Critical Load rating.

Research claim boundary
Peak-day water demand is treated as a necessary first-order utility service-capacity screen, not as a complete hydrologic carrying-capacity determination.
01 / Published baseline

The infrastructure signal becomes materially stronger at the peak.

The ratios below are Critical Load calculations using Loudoun Water's published baseline values. They should be read as ratios of published values, not as proof that each system and data-center maximum occurred at the same instant.

9.0%2.6 MGD / 29.0 MGD · published average-day values
16.0%8.0 MGD / 50.0 MGD · published maximum-day values
3.08×Data-center potable peak / average ratio
2.1–5.2MGD peak per added GW · official regional scenario range
~1.8×

The data-center peak/average ratio is about 1.8 times the system-wide peak/average ratio using the published baseline figures.

Peak first

An annual-average water metric can materially understate the service-capacity question relevant to large additions of compute.

Convert an explicit peak-water budget into compute without hiding the allocation assumption.

The PWCS starts from a declared maximum-day potable allocation. It deliberately does not call nominal future utility capacity “available headroom.”

Peak Water Capacity ScreenB = a × Cfuture − DDC,peak,current
Pscreen = max(0, B / Ipeak)

Illustrative v1.0 values: Cfuture = 90 MGD; a = 16%; current published data-center peak potable demand = 8 MGD. The 16% allocation is an E4 analyst scenario, not utility policy.

3.05 GWLow · 2.1 MGD/GW
2.21 GWMedium · 2.9 MGD/GW
1.23 GWHigh · 5.2 MGD/GW
0.75 GWFacility-high sensitivity · 8.5 MGD/GW
These are not estimates of “remaining Loudoun capacity.” They demonstrate the consequence of one explicit allocation rule and different cooling-intensity assumptions. A verified capacity result requires project-specific utility and hydrologic evidence.

Reclaimed supply can reduce potable burden without removing total consumption.

The method keeps water source and hydrologic consumption separate. This prevents reclaimed water from being treated as “zero water.”

Source and consumptionPotable burden = Dtotal × (1 − r)
Estimated consumption = Dtotal × c

v1.0 uses the ICPRB 75% consumptive factor only as a transparent regional-analysis sensitivity. Project cooling cycles, blowdown, discharge and seasonality should replace it when available.

Reclaimed sharePotable peak / +1 GW medium caseReclaimed peakConsumption sensitivity
0%2.90 MGD0.00 MGD2.175 MGD
50%1.45 MGD1.45 MGD2.175 MGD
100%0.00 MGD2.90 MGD2.175 MGD

The output is a screen and an evidence-request workflow.

Suitable forEarly-stage infrastructure decisions

Site screening; infrastructure diligence; cooling/source comparison; scenario comparison; utility data requests; framing project-specific evidence gaps.

Not suitable forFinal service or regulatory determination

Utility will-serve; hydraulic design; permit approval; drought allocation; water-right determination; final Critical Load rating.

01

Compute basis

Declare IT MW and project phasing.

02

Water boundary

Potable, reclaimed, watershed and discharge.

03

Peak evidence

Average plus maximum-day demand.

04

Cooling cases

Project WUP or explicit scenario bounds.

05

Escalate

Hydraulics, hydrology, drought and review before rating.

Paper → source register → inputs → code → model → scenario outputs.

The release package is designed so the headline arithmetic can be recomputed without trusting the website.

The next improvement is external evidence, not more decorative modelling.

v1.0 intentionally stops before a final water-constrained compute envelope. The unresolved gates are substantive: utility service/hydraulic evidence, project-specific seasonal WUP, low-flow and drought conditions, wastewater/blowdown treatment, project phasing and independent domain review.

Release interpretationUse this as a reproducible public working method for screening and diligence. Do not cite it as a peer-reviewed final carrying-capacity determination.

Cite the release at the strength it actually supports.

Critical Load Research Group (2026). Peak Water, Not Average Water: A reproducible public-evidence capacity screen for data-center growth in Loudoun County, Northern Virginia. CL-WP-004 / R04 / CL-P03 / CL-001. Working Paper v1.0, 19 September 2026. DOI pending.

Primary and official evidence remains identifiable.

The web summary does not replace the source register. Core inputs are linked below, while the downloadable CSV records evidence class, use, access path and limitations.

SourceRole in v1.0Open
Loudoun Water · Data Center Water UsePublished average-day, maximum-day and future permitted-capacity baselineSource ↗
Loudoun Water · Reclaimed Water ProgramLocal reclaimed-water context and service framingSource ↗
ICPRB · 2025 WMA Water Supply StudyRegional direct-water scenarios and planning contextStudy ↗
ICPRB · Data Centers and Water UsePeak, seasonality and consumptive-use contextSource ↗
R04 source registerMachine-readable evidence trail and evidence classesCSV →